Yazd
Solar Thermal Power Plant - IPDC
|
| Objective: |
| Implementation of the first Parabolic Trough Integrated Solar Combined Cycle System in Iran. |
| Project Description: |
| The feasibility
study of Integrated Solar Combined Cycle System ( I.S.C.C.S) has been performed by multinational consulting consortium led by the German company named Fichtner and with the participation of Pilkington Solar from Germany and Electric Research Center of Iran (Niroo). |
| According to a
feasibility study, Yazd Province, due to good solar resources has been selected for implemention of this project. Also the Integrated Solar Combined Cycle System was the technology which among other solar thermal configurations has been selected for this power plant. In order to achieve this goal we are in the process of performing the following activities: |
|
| TECHNOLOGYCAL
DESCRIPTION Parabolic Trough Technology |
| The Solar field
is comprised of parabolic trough mirrors and is connected to a natural gas combined cycle power plant. The option selected was to use two gas turbine units of 123.4 MW (ISO condition), a waste heat recovery steam generator and a steam of 198 MW for a total installed power of 414 MW. Total net electric power is 2917 GWhe. The Solar field is formed by LS-3 by LS-3 parabolic tough collectors ordered in 84 loops, the solar radiation is about 2515 kwh/m2 and thermal energy from solar field is almost 470 Gwh. The Solar field has been optimized to fulfil the plant requirements and to give solar a contribution of around %5.3 . The total area occupied would be around 366,240 m2 and the installed power of the solar field would be 67 MW and using the auxiliary firing for a total 1200 hours per year. The type of boiler for this system is HRSG while the condensation cooling will be achieved by indirect natural draft cooling tower with Heller system. |
|
Project financing: On a feasibility
study basis, it is estimated that the |
| Project
Implementation Several activities have been undertaken in relevance to the prepartion of the proposed project. In the period 1996-2001 a consortium of three companies Pilkington, Fichtner and Matn (power research center of Iran) prepared for IPDC a feasibility study (financial and technical feasibility) for possible plant configuration ranging from 215 MW (two gas turbine unit ) to 444 MW located in Yazd. |
| The installation
of two gas turbine units (Frame 9E PG9171 E,ISO ratins of 123.4MW) have
been completed as the first phase of an integrated solar combined cycle system. |
| At the moment our Consultant as well as our designer Moshanir Power Engineering Consultant is performing the following activities. |
|